Core switch replacement - Telehouse West from 2026-05-14 02:00 BST to 2026-05-14 05:00 BST
Scheduled maintenance
Nationwide City Fibre
Nationwide Ethernet
Nationwide OFNL
2026-05-14 02:00 BST
· 3 hours
Updates
Scheduled
April 10, 2026 · 15:16 BST
Planned maintenance — Telehouse West core switch replacement
We will be carrying out planned maintenance at Telehouse West as part of our continual improvement programme.
What we are doing:
-
Replacing core switches with new devices featuring higher port speeds and updated architecture
Who is affected: - Customers whose services are delivered via City Fibre or OFNL may experience a complete loss of service for the duration of the maintenance window
-
Customers whose services are delivered via other means may be disconnected for short periods whilst the service is moved to another datacentre automatically.
Expected duration: - The work is expected to be completed within 30 minutes
- A full 3-hour window has been reserved — customers should plan for this in full
We apologise for any inconvenience and thank you for your patience. If you have any questions, please contact our support team.